Evaluating the Time–Cost–Quality Trade-Off in the Design and Construction of Industrial Drinking and Demineralized Water Tanks: A Case Study from the Niger Delta, Nigeria

Clifford Onwuka, Chizindu Stanley Esobinenwu

Abstract

Construction projects frequently face competing requirements for timely delivery, budget control and conformance to specified quality. This study evaluates the time–cost–quality trade-off associated with the design and construction of industrial drinking-water and demineralised-water tanks for an oil and gas facility in Bonny Island, Rivers State, Nigeria. The study adopted an exploratory qualitative case-study design and relied on secondary evidence comprising published literature, industry sources and project planning/completion records. An inductive thematic analysis, informed by Braun and Clarke’s six-phase approach, was used to identify recurring mechanisms through which project decisions influence time, cost and quality. The project records indicate a planned contract value of US$5,533,150.70 and an approved quality requirement of 94.54%; the final varied value increased to US$7,183,313.44, while reported achieved quality declined to 86.15%. The project milestones also experienced substantial schedule slippage, with reported milestone delays ranging from 444 to 730 days. Eight integrated themes emerged: timely completion with quality and budget compliance; critical-path and procurement management; KPI- based performance control; benefits and limitations of experienced permanent crews; proactive risk identification; non-linear relationships between resource loading and duration; scope-change effects on TCQT; and the strategic use of external expertise and digital tools. The findings indicate that accelerating work through additional resources does not automatically reduce overall duration because activity dependencies, bottlenecks and coordination constraints may limit productivity. The study therefore proposes an integrated TCQT decision framework combining scope definition, critical-path analysis, procurement planning, risk and contingency management, standardised KPIs, lean practices, BIM/digital coordination, stakeholder communication and controlled external support. The framework provides a practical decision structure for industrial water-tank projects where quality and functional integrity cannot be sacrificed merely to recover schedule or reduce initial cost.

Keywords

Time–cost–quality trade-off; construction project management; industrial water tanks; demineralised water; critical path method; risk management; thematic analysis; Niger Delta; oil and gas. IJEMT

References

AACE International. (2004). Skills & knowledge of cost engineering. AACE International. Abd El-Karim, M. S. B. A., Mosa El Nawawy, O. A., & Abdel-Alim, A. M. (2017). Identification and assessment of risk factors affecting construction projects. HBRC Journal, 13(2), 202– 216. Ajmal, M. M., Khan, M., Gunasekaran, A., & Helo, P. T. (2022). Managing project scope creep in construction industry. Engineering, Construction and Architectural Management, 29(7), 2786–2809. Alavipour, S. R., & Arditi, D. (2019). Time-cost tradeoff analysis with minimized project financing cost. Automation in Construction, 98, 110–121. Anuar, N. I., & Ng, P. K. (2011). The role of time, cost and quality in project management. Proceedings of IEEE International Conference on Industrial Engineering and Engineering Management, 630–634. Ballesteros-Pérez, P. (2017). Modelling the boundaries of project fast-tracking. Automation in Construction, 84, 231–241. Banihashemi, S. A., Khalilzadeh, M., Shahraki, A., Malkhalifeh, M. R., & Ahmadizadeh, S. S. R. (2021). Optimization of environmental impacts of construction projects: a time–cost– quality trade-off approach. International Journal of Environmental Science and Technology, 18, 631–646. Braun, V., & Clarke, V. (2006). Using thematic analysis in psychology. Qualitative Research in Psychology, 3(2), 77–101. Castleberry, A., & Nolen, A. (2018). Thematic analysis of qualitative research data: Is it as easy as it sounds? Currents in Pharmacy Teaching and Learning, 10(6), 807–815. Elbeltagi, E., Ammar, M., Sanad, H., & Kassab, M. (2016). Overall multiobjective optimization of construction projects scheduling using particle swarm. Engineering, Construction and Architectural Management, 23(3), 265–282. El-kholy, A. M. (2013). Time–cost tradeoff analysis considering funding variability and time uncertainty. Alexandria Engineering Journal, 52(1), 113–121. El-Rayes, K., & Kandil, A. (2005). Time-cost-quality trade-off analysis for highway construction. Journal of Construction Engineering and Management, 131(4), 477–486. Feylizadeh, M. R., Mahmoudi, A., Bagherpour, M., & Li, D. F. (2018). Project crashing using a fuzzy multi-objective model considering time, cost, quality and risk under fast tracking technique: A case study. Journal of Intelligent & Fuzzy Systems, 35(3), 3615–3631. Fu, F., & Zhang, T. (2016). A new model for solving time-cost-quality trade-off problems in construction. PLoS ONE, 11(12). Gondia, A., Siam, A., El-Dakhakhni, W., & Nassar, A. H. (2020). Machine learning algorithms for construction projects delay risk prediction. Journal of Construction Engineering and Management, 146(1), 04019085. Habibi, M., Kermanshachi, S., & Rouhanizadeh, B. (2019). Identifying and measuring engineering, procurement, and construction key performance indicators and management strategies. Infrastructures, 4(2), 14. Hammad, A. W., Sutrisna, M., & Zaman, A. (2019). Towards optimising OSM implementation in construction projects. In Offsite Production and Manufacturing for Innovative Construction: People, Process and Technology (pp. 189–222). Routledge. IJEMT Hamta, N., Ehsanifar, M., & Sarikhani, J. (2021). Presenting a goal programming model in the time-cost-quality trade-off. International Journal of Construction Management, 21(1), 1– 11. Hegazy, T. (2002). Computer-Based Construction Project Management. Prentice Hall. Hegazy, T., & Menesi, W. (2010). Critical path segments scheduling technique. Journal of Construction Engineering and Management, 136(10), 1078–1085. Hennink, M., Hutter, I., & Bailey, A. (2020). Qualitative Research Methods. Sage. Hinze, J. W. (2004). Construction Planning and Scheduling. Pearson Prentice Hall. Jeunet, J., & Orm, M. B. (2020). Optimizing temporary work and overtime in the time cost quality trade-off problem. European Journal of Operational Research, 284(2), 743–761. Kazaz, A., Ulubeyli, S., Er, B., & Acikara, T. (2016). Construction materials-based methodology for time-cost-quality trade-off problems. Procedia Engineering, 164, 35–41. Keshk, A. M., Maarouf, I., & Annany, Y. (2018). Special studies in management of construction project risks. Alexandria Engineering Journal, 57(4), 3179–3187. Kiger, M. E., & Varpio, L. (2020). Thematic analysis of qualitative data: AMEE Guide No. 131. Medical Teacher, 42(8), 846–854. Lotfi, R., Yadegari, Z., Hosseini, S., Khameneh, A., Tirkolaee, E., & Weber, G. (2022). A robust time-cost-quality-energy-environment trade-off with resource constraints in project management. Journal of Industrial and Management Optimization, 18(1). Luong, D. L., Tran, D. H., & Nguyen, P. T. (2021). Optimizing multi-mode time-cost-quality trade-off of construction project using opposition multiple objective difference evolution. International Journal of Construction Management, 21(3), 271–283. Monghasemi, S., Nikoo, M. R., Fasaee, M. A. K., & Adamowski, J. (2015). A novel multi-criteria decision-making model for optimizing time–cost–quality trade-off problems in construction projects. Expert Systems with Applications, 42(6), 3089–3104. Mungle, S., Benyoucef, L., Son, Y. J., & Tiwari, M. K. (2013). A fuzzy clustering-based genetic algorithm approach for time–cost–quality trade-off problems. Engineering Applications of Artificial Intelligence, 26(8), 1953–1966. Nasiri, S., & Lu, M. (2022). Streamlined project time-cost trade-off optimization methodology: Algorithm, automation, and application. Automation in Construction, 133, 104002. Nguyen, D. T., Le-Hoai, L., Tarigan, P. B., & Tran, D. H. (2022). Trade-off time cost quality in repetitive construction project using fuzzy logic approach and symbiotic organism search algorithm. Alexandria Engineering Journal, 61(2), 1499–1518. Orm, M. B., & Jeunet, J. (2018). Time cost quality trade-off problems: a survey exploring the assessment of quality. Computers & Industrial Engineering, 118, 319–328. Pollack-Johnson, B., & Liberatore, M. (2006). Incorporating quality considerations into project time/cost trade-off analysis and decision making. IEEE Transactions on Engineering Management, 53(4), 534–542. Rachid, Z., Toufik, B., & Mohammed, B. (2019). Causes of schedule delays in construction projects in Algeria. International Journal of Construction Management, 19(5), 371–381. Safapour, E., & Kermanshachi, S. (2019). Identifying manageable scope creep indicators and selecting best practice strategies for construction projects. Proceedings of the CSCE International Construction Specialty Conference, 12–15. IJEMT Shankar, N. R., Raju, M. M. K., Srikanth, G., & Bindu, P. H. (2011). Time, cost and quality trade- off analysis in construction of projects. Contemporary Engineering Sciences, 4(6), 289– 299. Shishodia, A., Dixit, V., & Verma, P. (2018). Project risk analysis based on project characteristics. Benchmarking: An International Journal, 25(3), 893–918. Siraj, N. B., & Fayek, A. R. (2019). Risk identification and common risks in construction: Literature review and content analysis. Journal of Construction Engineering and Management, 145(9). Son, P. V. H., & Khoi, L. N. Q. (2022). Utilizing artificial intelligence to solving time–cost–quality trade-off problem. Scientific Reports, 12, 20112. Tavana, M., Abtahi, A. R., & Khalili-Damghani, K. (2014). A new multi-objective multi-mode model for solving pre-emptive time–cost–quality trade-off project scheduling problems. Expert Systems with Applications, 41(4), 1830–1846. Tran, D. H., Luong-Duc, L., Duong, M. T., Le, T. N., & Pham, A. D. (2018). Opposition multiple objective symbiotic organisms search for time, cost, quality and work continuity tradeoff in repetitive projects. Journal of Computational Design and Engineering, 5(2), 160–172. Wang, T., Abdallah, M., Clevenger, C., & Monghasemi, S. (2021). Time–cost–quality trade-off analysis for planning construction projects. Engineering, Construction and Architectural Management, 28(1), 82–100. Webb, C., Gao, L., & Song, L. G. (2016). Schedule compression impact on construction project safety. Frontiers of Engineering Management, 2(4), 344–350. Zhang, L., Du, J., & Zhang, S. (2014). Solution to the time-cost-quality trade-off problem in construction projects based on immune genetic particle swarm optimization. Journal of Management in Engineering, 30(2), 163–172.

More Articles from INTERNATIONAL JOURNAL OF ENGINEERING AND MODERN TECHNOLOGY